Differing length of work weeks

S

Sherry

Let's say I have a project and two separate groups of people are doing the
work. One group works 5 days a week, the other works 6 days a week. How can
I enter durations as a number of weeks if there are 2 different defintions
of "week?" Do I have to enter everything in terms of days?
 
G

Gérard Ducouret

Hello Sherry,

You have point out the solution : while you have 2 different length of
weeks, you have to enter all the durations in terms of days.

Gérard Ducouret
 
S

Sherry

That's what I'm trying to avoid. If I say that something that starts on
Monday last 6 days the final day will be the next Monday if Saturday and
Sunday aer off days. It'll be Saturday if only Snday is an off day. Neither
is right for both groups.
 
G

Gérard Ducouret

Don't forget to set *resource calendars* with 5 or 6 days a week !
You have to create these 2 calendars and to assign them to each kind of
resource.

Gérard Ducouret
 
S

Sherry

Great - thanks!!!!!

Gérard Ducouret said:
Don't forget to set *resource calendars* with 5 or 6 days a week !
You have to create these 2 calendars and to assign them to each kind of
resource.

Gérard Ducouret
 
S

Steve House

There are two issues here and Gerard's answer is only partially correct.
He is correct to say that you need to create two resource calendars, one
defining the work hours for the 5 day a week people and the other for
the 6 day a week people - you absolutely need to do that. But when you
enter the task duration estimate initially you will need to use days
instead of weeks the entries. The reason is that Project actually
stores duration in minutes. The entries on the Calendar Options page
(Tools, Options menu) for "Hours per Day" and "Hours per Week" are the
values used for the conversion factors from what you enter and what is
stored in the database and this happens before the resources are
assigned and it knows what calendar to apply. So with the default
settings, when you type in a duration as "2 weeks" Project converts that
to 2*40*60=4800 minutes and that is what stored in the database. Then
when you assign resources it looks at the resource calendars to see
which minutes thru the day count towards that 4800 minute duration.
Lets say it begins Monday 8am and people work either 8 hours per day 5
days a week or 8 hours a day 6 days a week. At 8 hours per day, each
group's workday will account for 480 minutes. If someone from the first
group is assigned it will show "2 weeks" task starting Mon at 8 and
finishing a week from Fri at 5pm. If you assign the same 2 week task to
someone in the 2nd group, it will show the task beginning Mon at 8am and
finishing a week from THURSDAY at 5pm, the day before it would finish
with the other group.

If it's any consolation, you probably should be breaking down your tasks
into smaller units anyway. Tasks that have durations more than about 2
weeks usually are too large to effectively manage and should be broken
down into smaller components.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top