Disable entry timesheet for Milestone task?

V

Vincent

In View My Task screen, can we disable timesheet's entry (eg. Percent Work
Completed, Remaining Hours, etc.) just for Milestone task?
 
R

Reid McTaggart

The best practice is not to assign milestone tasks to resources. That leaves
it to the Project Manager to determine when a milestone has been achieved and
to mark it complete in the schedule.
 
J

John L

We have been assigning a resource to milestone tasks, and our work-around is
to use the arbitrary "0.1 Hrs" to complete the milestone task. This allows
our resource to complete the task, and they simply enter.1 Hrs to complete
the milestone.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top