Log into PWA with administrator permissions. Click the Admin menu, then
click Customize Project Web Access. In the Time Period Settings section,
select the Non Managed Periods option. Hope this helps.
--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado http://www.msprojectexperts.com
"We wrote the book on Project Server"
this option does not appear in MS Project Server 2002. I am trying to load
actuals from an mpp file into project server 2002, but all historical
actuals are zeros! I am trying to follow your instructions from the post:
Nevermind...got it. Since managed time periods dont exist in 2002, just
eliminate that step from the instructions.