Disabled Functions

D

Don

Last week MS Project failed to open correctly and I received an error message
asking me if I wanted to open in safe mode. I ignored since not sure what
this meant. Apparently my global template was corrupted and when I later
re-installed the app I went through option setup for views and formats.
However, two areas still do not function correctly (1) summary tasks do not
reflect the start / end dates of child tasks on existing schedules or new
schedules. Changes in durations are ignored (and there is no baseline). (2)
dependencies do not seem to work. I can add dependency to a task but appears
to have no effect.

Would appreciate assistance in reactivating these features. Thanks
 
J

JulieS

Hello Don,

Is your calculation mode set to manual? Check Tools > Options
Calculation tab and ensure the mode is set to automatic.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
D

Don

Thanks Julie. That was a simple setting change. I thought default was
automatic recalc, but I guess not or it changed. Appreciate your help.
 
J

JulieS

You're welcome Don. Glad to know if was an easy fix and thanks for
the feedback.
Julie
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top