DISABLING ACCEPT TASK CHANGES

M

MARVS

Hi,


Hope you can help me with my problem…

I am implementing an EPM solution using MS Project Server 2k3 in one of our
clients here in Manila.
I am done with the envisioning part and now working on the planning part.
One of their requirements is to disable the approval process every time the
team members have tasks changes. Or simply they want to remove the accept
part on the part of the project managers web access. I already used the rule
command on the update page but its functionality is the same with the update
button on the upper right part of the page. How can I remove or disable that
functionality?
 
D

Dale Howard [MVP]

MARVS --

You cannot. Microsoft's assumption is that project managers need to be at
least minimally involved with the task update approval process. The use of
Rules can speed up this process, but the PM must click the Run Rules Now
button to approve task updates waiting for approval. Hope this helps.
 
D

Dale Howard [MVP]

MARVS --

You cannot. Microsoft's assumption is that project managers need to be at
least minimally involved with the task update approval process. The use of
Rules can speed up this process, but the PM must click the Run Rules Now
button to approve task updates waiting for approval. Hope this helps.
 