Disappearing Tasks & Data when file is printed to PDF

M

Missing Tasks

Hello,

I have MS Project 2003 with SP3. When I print to PDF the files the file
that I have I lose all of the information when there are more than 22 tasks
per page. I do not lose the sequencing. I just lose the Data associated
with the task. This includes the Name, Resources and Dates.

I seem to be able to print the document with the data as long as there are
less than 22 items per page.

Any help would be appreciated.
 
D

Dave

I suspect that this is an issue with the PDF generation software rather
than Project.

As a work around you cold paste your plan into something like Word and
print that.
 
M

Missing Tasks

Actaully I used Primo PDF and it worked fine.

Thanks that is a good work around I will keep in mind.