A
Alfatcop
Hello All,
Working on Project Server 2007:
Logging as the Admin (and not as the status Manager), I see the following:
- In PWA>Project details, one early task of the project is at 0% completion
- In Project Pro, the same task is at 100% completion.
I then republished the project, the task in PWA is now at 100% completion.
Here is my question:
Could it be possible as an Admin that I was able to see the project in
Project Pro in its unpublished version (=saved state by the status Mgr)?
Thanks for your help,
Alexandre
Working on Project Server 2007:
Logging as the Admin (and not as the status Manager), I see the following:
- In PWA>Project details, one early task of the project is at 0% completion
- In Project Pro, the same task is at 100% completion.
I then republished the project, the task in PWA is now at 100% completion.
Here is my question:
Could it be possible as an Admin that I was able to see the project in
Project Pro in its unpublished version (=saved state by the status Mgr)?
Thanks for your help,
Alexandre