Discrepancy between View Resource Assignments and Adjust Actuals andOLAP cube

J

jlg

Greetings,

I have a resource that is showing 7 hrs of actual work on Friday, 8th
February - in both the OLAP cube and in the 'adjust actuals' view of
PWA (and also in the MS Project plan). However, these 7 hrs are not
showing in the 'View Resource Assignments" view of PWA... The task is
not showing in View Resource Assignments at all... we have republished
it and the resource is set to committed.

We are using Project Server 2003 and managed periods.

Any ideas on why it would not be included in the View Resource
Assignments view?


Thank you,
Jlg
 
J

Jackson T. Cole

Ensure you are looking at "All Assignments". If the task should be showing
up in "Current Assignments" but isn't, that is another problem. Just try "all
...." first!

FWIW ...

JTC
 
J

jlg

   Ensure you are looking at "All Assignments". If the task should be showing
up in "Current Assignments" but isn't, that is another problem. Just try "all
..." first!

   FWIW ...

JTC









- Show quoted text -

JTC -

What a silly question I had - yes, i know very well 'all assignments'
- but for whatever reason - i failed to recall that one - those hrs
are there. Thanks for pointing out the obvious to me!

Cheers,

jlg
 