I am baffled by this problem. I have a resource assigned to a task with just
8 hours of work. The duration is 1 day, and the unit is 100%.
When I go to the Task Usage screen, this same resource is showing 40 hours
of work for the same task. It shows 30 hours for one day, and 10 for
another, even though on the Gnatt chart is say 8 hours and 1-day duration.
Any one know what could cause this?
Joe