Discrepency between timephase and task fields

S

ST

Hi,

I have "several" files were I have noted differences between what is shown
in a task field and the sum of the timephased. Is this normal?

For instance my Project Level Task Baseline cost = $289,051.16
The timephased sums to = $289,024.47
Although in this case it is only about 26$, I find these discrepencies often
enough and I can't explain them.

So, in this case I resbaseline... now I have baseline cost of $290,300.17 at
the task level, and $290,281.00 timephase (sum).
A difference of 19$. So, what is few dollars between friends you say???!!!

Is this normal????

In this case I'm using MS Pro 2003 SP3.

/Spiro.
 