E
Evadbass
We have projects and tasks that can last over several years. I would like to
create columns to display the cost for the tasks on an annual basis. My
current project has a one column each for 2007, 2008 & 2009, as well as a
total cost column. I can display these costs in the cost reports, but I am
unable to display them in the columns when looking at the Gantt Chart. I
figure I need to develop a formula for the calculation, but I do not know how
to calculate the costs using the year as a time constraint.
Any help would be greatly appreciated!!
create columns to display the cost for the tasks on an annual basis. My
current project has a one column each for 2007, 2008 & 2009, as well as a
total cost column. I can display these costs in the cost reports, but I am
unable to display them in the columns when looking at the Gantt Chart. I
figure I need to develop a formula for the calculation, but I do not know how
to calculate the costs using the year as a time constraint.
Any help would be greatly appreciated!!