Hi all,
I am trying to display Baseline Start and Baseline Finish dates on My Tasks
page, in My Assignments view.
I am creating a custom field with forumla of [Baseline Start] then add it to
enterprise fields. Then I set baseline of the project, save and publish to
project server.
My custom field which displays Baseline dates are being displayed as
expected on Project Professional but not on PWA. In pwa, the column shows up
but is empty.
Any help is appreciated.