Display Baseline work at timesheet view in PWA-MSP-2003

W

WDP

Hello Team,
To help the team determine if they are tracking to budget on
a work plan task it is helpful to see the baseline work effort for each task.
This field is shown in the Timesheet view however no information is displayed
in this field.

A workaround is for me to export the work plan to a spreadsheet and people
look at this to determine if over/under budget. However it would be much
easier for team members if we could change the Timesheet view.

Can the timesheet view be changed?


-WDP
 
W

WDP

Hello Dale,
Thanks for the prompt response.

I did check the fields at timesheet view and 'Baseline work ' is present.

But at the timesheet view, this field displays no data.

Please update.

Regards-WDP
 
D

Dale Howard [MVP]

WDP --

Read the rest of the FAQ! Your PMs need to add the Baseline Work field to
the list of Published fields in EVERY project and then republish the
assignments. Hope this helps.
 