Display Milestone Rollup

C

CB

I am using MSOP 2007. I have a schedules that has numerous summary tasks. I
have a section of deliverables under one of the summary tasks. This summary
task is at level 3 in the schedule. I would like to show on the deliverables
summary task only each individual deliverable.

Such as:

Jan 10 Feb 10
Deliverable Summary <> <>
Unit 1 <>
Unit 2 <>

I don't want to show these on all summary tasks.

Can this be done?
 
G

Gérard Ducouret

Hi CB,
It's possible : double click the summary which will not display the rolled
up milestones, to open the Summary Task Information dialog.
In the General tab, uncheck the Show rolled up Gantt bars option.

Gérard Ducouret
 
C

CB

Hi Gérard,

I tried this and it did not work for me. I would like to show on the
summary line the diamond shapes over time for each deliverable.
 
G

Gérard Ducouret

CB,

The option I stated was the last one. Before that you have to check the
"Roll up Gantt bar to summary" option in the General tab of Task
Information, for each deliverable.
For the summary which will receive the rolled up milestones, you would like
to check the option : Hide task bar.

Hope this helps,

Gérard Ducouret
 
M

Mike Glen

Hi CB,

I don't believe this is possible as you present it. If you roll up the
milestone to the summary, it will appear on all the summaries above it, you
can't select which summary to roll up to.


FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials

CB wrote:
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top