C
CB
I am using MSOP 2007. I have a schedules that has numerous summary tasks. I
have a section of deliverables under one of the summary tasks. This summary
task is at level 3 in the schedule. I would like to show on the deliverables
summary task only each individual deliverable.
Such as:
Jan 10 Feb 10
Deliverable Summary <> <>
Unit 1 <>
Unit 2 <>
I don't want to show these on all summary tasks.
Can this be done?
have a section of deliverables under one of the summary tasks. This summary
task is at level 3 in the schedule. I would like to show on the deliverables
summary task only each individual deliverable.
Such as:
Jan 10 Feb 10
Deliverable Summary <> <>
Unit 1 <>
Unit 2 <>
I don't want to show these on all summary tasks.
Can this be done?