D
dee
Hi,
If a resource is on vacation for a day, for example, and is assigned a task
with a duration of 3 days, I see on the Gantt Bar that the task is taking
place over 4 days to compensate for the vacation day.
I can display non-working days in the Calendar easily, but am wondering how
I can display the non-working times for a resource in a task gantt bar.
If a resource is on vacation for a day, for example, and is assigned a task
with a duration of 3 days, I see on the Gantt Bar that the task is taking
place over 4 days to compensate for the vacation day.
I can display non-working days in the Calendar easily, but am wondering how
I can display the non-working times for a resource in a task gantt bar.