Does anyone know if there's a way to display individual resources' nonworking
time on the Gantt chart. I've set up the individual resource calendars with
vacation days, and it skips the days correctly when I'm entering tasks. It's
just not visually apparent when you look at the Gantt, and thought it would
be beneficial if those non-working days would appear.

Much appreciate if anyone has any ideas. Thanks, Barry
 
J

Jan De Messemaeker

Hi,

That's easier said than done.
You can read some about this in the article on my website.
HTH
 
B

Barry

Jan;
Thank you. I was hoping the bar representing the task could either change
color during the non-working time or show ....., like when it splits a task.
I tried the resource leveling but I think it's going to be so difficult
maintaing from an administrative point, since I'll have to prioritize the
tasks to make sure they get leveled in a certain order every time I enter
another non-working entry in the calendar.
Thanks again. Your article was very informative. Barry
 