S
Sue
Is there a way that I can format task Start and finish dates to display the
number of working days from the start of a project?
For example,
Start: 8/9 Finish 8/11 shows as Day 1 - Day 3
Start: 8/14 Finish 8/21 shows as Day 4 - Day 9
I want the day numbers to take into account non-working days from the
project calendar. This is different than changing the timescale in the Gantt
view to Day1, Day2 because the timescale does not adjust for non-working
days. I have tried using a formula in a custom field to calcuate the
difference between the date and the project start date, but that method also
does not account for non-working days (at least not that I could find).
Any help is greatly appreciated.
Make it a great day!
number of working days from the start of a project?
For example,
Start: 8/9 Finish 8/11 shows as Day 1 - Day 3
Start: 8/14 Finish 8/21 shows as Day 4 - Day 9
I want the day numbers to take into account non-working days from the
project calendar. This is different than changing the timescale in the Gantt
view to Day1, Day2 because the timescale does not adjust for non-working
days. I have tried using a formula in a custom field to calcuate the
difference between the date and the project start date, but that method also
does not account for non-working days (at least not that I could find).
Any help is greatly appreciated.
Make it a great day!