Display Resource Name in Portfolio Analyzer who have no work assig in Proj pro 2003

N

Nitesh Mathur

Resources who have no work assign ,their names are not display in Portfolio
Analyser. We required their name to be display in Portfolio Analyser and
their actual work will be display 0hrs.


Any Body Help

Thanks

Nitesh
 
G

Gary L. Chefetz [MVP]

Nitesh:

Assignment data is assignment data, Therefore, if you create no assignment
data for a resource, then the resource doesn't get picked up in the
assignment calculations. Perhaps creating some actual assignment data in a
past period might be a solution for you.

--

Gary L. Chefetz, MVP
MSProjectExperts
For Project Server Consulting: http://www.msprojectexperts.com
For Project Server FAQS: http://www.projectserverexperts.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top