Display unit in Resource Availabilty

R

Ryan

Dear all,

I would like to know if it is possible to set the display unit of resource
availability view of resource center from hours to days?

Thanks,
Ryan
 
G

Gagan Goel - MCP PMP

Ryan,

I think the answer is no with out of the box funtionality, as the resource
availability views cannot be modified outside of view opitons available on
that page. But I have two possible workaroaunds for you.

Option 1
You can design a similar data analysis/portfolio analyzer view where you
have more flexibility in changing the units or creating a formula which
converts hours to days or hours to FTEs etc. You have to build the cube
successfully to make this option running.

Option 2
You can export the data to excel and convert values there based on a formula

Hope this helps. Please do considering rating this post if you feel it was
helpful.