R
Ryan
Dear all,
Although I have set the "Work is entered in" as Days in
"Options->Schedule", the unit in "Work" in the Resource Usage View in
Resource level is displayed as hours. However, in task level, they are
displayed as Days. Does anyone know why? Thanks in advance.
Rgds,
Ryan
Although I have set the "Work is entered in" as Days in
"Options->Schedule", the unit in "Work" in the Resource Usage View in
Resource level is displayed as hours. However, in task level, they are
displayed as Days. Does anyone know why? Thanks in advance.
Rgds,
Ryan