Displayed 'Total Slack' Value Shows Zero

R

RSBrunton

* Using MSP 2003 and last task in chain has 'Deadline' set
* Gantt shows end of last task being 'to the right' of the Deadline
inverted-arrow
--> should have a negative Total Slack number
* In chain of tasks in critical path, the first ones show non-zero Total
Slack, then suddenly Total Slack value goes to zero from that point on

Is there a task property or something that has the effect of driving Total
Slack to zero?
 
R

RSBrunton

Thanks, Jan ... fyi, all tasks in the critical path are ASAP and none are
marked as complete. Perhaps I can restate:

The first 'n' tasks in the critical path *do* show Total Slack numbers,
then, from 'n+1' through the last task, the Total Slack numbers are zero.

I have inspected the tasks at the transition (i.e. 'n' to 'n+1') and believe
they are no different that any other.

Any other properties to look at or project-level settings to consider?
 