* Using MSP 2003 and last task in chain has 'Deadline' set
* Gantt shows end of last task being 'to the right' of the Deadline
inverted-arrow
--> should have a negative Total Slack number
* In chain of tasks in critical path, the first ones show non-zero Total
Slack, then suddenly Total Slack value goes to zero from that point on
Is there a task property or something that has the effect of driving Total
Slack to zero?