Displaying Baseline Start and Finish on the Task view timesheet

D

Dots

Hi,
I have been able to add the Baseline Start and Baseline Finish fields to the
timesheet view, but the data (dates) does not display. Is this a function of
data maintained in the cube? If I can get baseline dates in Profolio
analysis, why would that same data not appear on the timesheet in those
respective columns?

Please advise how I can get the data to display in timesheet. Thanks!

dots.
 
D

Dots

Thanks, Dale. I Just tried this and now get an NA in these fields in the
timesheet view? Do I need to wait for some cube update to occur?
 
D

Dots

Dale,
As a follow-up, I had another PM try these instructions and real dates
appeared on the time sheet. I appreciate your assistance and we are good to
go!

Thanks!
 