displaying critical path

S

swell estimator

after going through the steps to get the CP to display a yellowish
highlighting appeared to the left & top & below the tasks column. But I
expected the critical path, default color red to display in the Gantt chart
showing on my monitor screen.

It wasn't there so I dug around in the instructions and saw something about
formatting the critical p. using the Gantt Chart wizard. But then I couldn't
find the wizard.

What am I doing wrong? I've never tried to display the cp below.

thank you in adavnce - Swell
 
S

Steve House [MVP]

In the Gantt Chart view, right mouse click on the right-hand half of the
screen, the graphical side. You'll find the Gantt Chart Wizard listed on
the context menu.
 