T
TESA0_4
I have some VBA knowledge but know zip about MS Project. I'm using Project to
display an aircraft servicing schedule prepared in Excel. The need is to
display in a 'Text' or 'Number' column in Project the number of days between
the planned start of a servicing and the planned finish date of its (single)
predecessor. I can't figure out how to give a variable defined as a task the
value it needs to get the finish date of the predecessor task.
I'm sure this is a dead-simple question for even a Project novice so I hope
someone can help.
Thanks for any help that you can offer.
display an aircraft servicing schedule prepared in Excel. The need is to
display in a 'Text' or 'Number' column in Project the number of days between
the planned start of a servicing and the planned finish date of its (single)
predecessor. I can't figure out how to give a variable defined as a task the
value it needs to get the finish date of the predecessor task.
I'm sure this is a dead-simple question for even a Project novice so I hope
someone can help.
Thanks for any help that you can offer.