A
A. Faisal Shaazi, PMP
Hi group,
Is there a way of displaying elapsed duration in addition to task duration?
I would like to create a view that shows the task duration as e.g. 3 days
and the elasped duration as 5 days (if the 3 days spans over a 2-day
nonworking weekend).
Any ideas?
Thank you.
A. Faisal Shaazi, PMP
Subang Jaya
Malaysia
Is there a way of displaying elapsed duration in addition to task duration?
I would like to create a view that shows the task duration as e.g. 3 days
and the elasped duration as 5 days (if the 3 days spans over a 2-day
nonworking weekend).
Any ideas?
Thank you.
A. Faisal Shaazi, PMP
Subang Jaya
Malaysia