L
Lisa Graham
I have a project in which I want to assign resources. I have set up working
times for all my resources so I will know when each is available to work.
When I go to a task to assign a resource, I want to be presented with a list
of only those resources who are available during the duration of that task.
For example, I have task during the first week of March and only 3 of my 4
resources can work during that week. Can Project show me just those 3? Is
this possible?
Thanks,
Lisa
times for all my resources so I will know when each is available to work.
When I go to a task to assign a resource, I want to be presented with a list
of only those resources who are available during the duration of that task.
For example, I have task during the first week of March and only 3 of my 4
resources can work during that week. Can Project show me just those 3? Is
this possible?
Thanks,
Lisa