B
Bobg
We typically set up our programming tasks as follows:
PrototypeA
Develop first iteration
Review
Develop 2nd iteration
Review
PrototypeB
Develop first iteration
Review
Develop 2nd iteration
Review
Whenever the information is displayed in the Resource Usage view, the only
description displayed is, for example, Develop first iteration and I do not
know if it applies to the task for PrototypeA or PrototypeB. I know that as a
work-around, I can change our task naming conventions, but before I go
through that process I wanted to make sure that there is not a way to display
the name(s) of the tasks that a given task rolls up to (in the Resource Usage
view).
Thanks!
PrototypeA
Develop first iteration
Review
Develop 2nd iteration
Review
PrototypeB
Develop first iteration
Review
Develop 2nd iteration
Review
Whenever the information is displayed in the Resource Usage view, the only
description displayed is, for example, Develop first iteration and I do not
know if it applies to the task for PrototypeA or PrototypeB. I know that as a
work-around, I can change our task naming conventions, but before I go
through that process I wanted to make sure that there is not a way to display
the name(s) of the tasks that a given task rolls up to (in the Resource Usage
view).
Thanks!