Hi ,
when any resource leave the company I deactivate him.and delete the resource
from manager category . but when the manager update the task hours of other
resources the message box is displaying again and again.
the message box is :
" This Project has inactive enterprise resources with remaining work.
Inactive enterprise resources such as:
win.bobsmith
have remaining work in the project . inactive resources will be unable to
report status so their remaining work should be assigned to active
resources."
although the manager change the remaining work to "0" of leaving resource .
and update in the project . but this message is displaying 4 to 5 time
whenever the user update the working hours of other resources.
regards
micheal
when any resource leave the company I deactivate him.and delete the resource
from manager category . but when the manager update the task hours of other
resources the message box is displaying again and again.
the message box is :
" This Project has inactive enterprise resources with remaining work.
Inactive enterprise resources such as:
win.bobsmith
have remaining work in the project . inactive resources will be unable to
report status so their remaining work should be assigned to active
resources."
although the manager change the remaining work to "0" of leaving resource .
and update in the project . but this message is displaying 4 to 5 time
whenever the user update the working hours of other resources.
regards
micheal