M
Michael
Hi,
I am facing a peculiar problem. I have two phases in my
project plan. First is a set of artifacts that i need to
prepare for the project (part of pre project planning).
The second is the actual project execution.
For example, for project initiation, i need to prepare a
presentation. The project initiation task is in phase 2
and the presentation preparation is in phase 1. I want to
show the WBS of the phase 2 task in the name of the phase
1 task. For example: phase 1 task should be displayed as
Ref: 1.2.1.2 Prepare Initiation Presentation
Where the 1.2.1.2 is WBS of the Project Initiation
activity.
This is akin to bookmark / reference funtionality of Word.
Do we have similar functionality in MS Project.
Michael
I am facing a peculiar problem. I have two phases in my
project plan. First is a set of artifacts that i need to
prepare for the project (part of pre project planning).
The second is the actual project execution.
For example, for project initiation, i need to prepare a
presentation. The project initiation task is in phase 2
and the presentation preparation is in phase 1. I want to
show the WBS of the phase 2 task in the name of the phase
1 task. For example: phase 1 task should be displayed as
Ref: 1.2.1.2 Prepare Initiation Presentation
Where the 1.2.1.2 is WBS of the Project Initiation
activity.
This is akin to bookmark / reference funtionality of Word.
Do we have similar functionality in MS Project.
Michael