Displaying Week-ends as shaded even though they are working days [GANNTT View]

K

KMD

Can Week-ends and Holidays be showed in the shaded manner even though they
have be desiganated to be working days?

KMD
 
R

Rob Schneider

Yes. See Menu: Format/Timescale, Tab: Non-working time.

Hope this is useful to you. Let us know.

rms
 
J

Jan De Messemaeker

Hi KMD,

The answer to your question taken as such is No.
But there is a nice workaround.
Leave the weekends as non working time
Make weekends working time for all resources.
Work will then be scheduled during weekends (at least for tasks having at
least one resource assigned to) but Sat-Sun will still be grey in the Gantt
Chart.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
 
J

John Beamish

I think that's the opposite of KMD's request. Sat/Sun *are* working time
(albeit non-standard working time).

I was unable to make Sat/Sun working days *and* give them a greyscale.


Yes. See Menu: Format/Timescale, Tab: Non-working time.

Hope this is useful to you. Let us know.

rms ++



--
 
G

Gérard Ducouret

Hello everybody,

It's easy to meet the KMD's request by using a 2nd calendar :
- Standard calendar : I guess that it has been customized with Saturdays
and Sundays as non working time. That's the Project's calendar that you can
check in : Project / Project Information / Calendar..
- On the timescale, you can display another calendar which could be a copy
of the Standard one *before* the changes. Format / Timescale... /
Non-Working time / Calendar : 2nd calendar

Gérard Ducouret
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top