J
Jim Aksel
I think many of us would like to see this.
It is very challenging to maintain proper Earned Value when Project
continuously adjusts work/remaining work/remaining costs, etc. by Actual
values. Even with allowing Project to Calculate Actuals field turned off,
this is still a problem. There are certain fields that use the Actual Cost
or Actual Work field in later calculations.
Example: A task is scheduled for 80 hours and 10 business days, fixed work,
baselined, worker gets paid $10/hr. On the status date, the worker says "I
am 25% complete, but it has taken me 30 hours to get this far." The problem
is that if I enter 25% complete into project, the Actual Work column changes
to 20 hours. This is incorrect ... his actual work is 30 hours. If I change
Actual work to 30 hours, the %Work Complete changes. Wrong. If I enter an
Actual Cost of $300, the CPI calculates correctly. However, I am being
mislead in that I am inferring that 20 hours of "real work" cost me $300. In
reality, I may have underbid the task and assumed the worker was more
efficeint than actual performance.
It is my opinion that I should be able to take "time card data" or "actuals"
from a separate accounting system and send these to Actual Work/Actual Cost
and have things calculate correctly. Otherwise, I am leaving it up to my
worker to say... "Well, I am 25% complete but I have only been working x% as
effectively as my bid so my ACWP is $300 or 30 hours"
I feel I need a better match between Actual Work and Actual Cost. Actual
Work (to me, time card values) has very little to do with the Work
Completed... work completed is BCWP and it has nothing to do with cost or a
time card entry.
So, please agree or educate me. Thanks
jim
I feel we need to be able to take "time card data" and enter it in to actual
work.
----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.
http://www.microsoft.com/office/com...afa9-2dea60746828&dg=microsoft.public.project
It is very challenging to maintain proper Earned Value when Project
continuously adjusts work/remaining work/remaining costs, etc. by Actual
values. Even with allowing Project to Calculate Actuals field turned off,
this is still a problem. There are certain fields that use the Actual Cost
or Actual Work field in later calculations.
Example: A task is scheduled for 80 hours and 10 business days, fixed work,
baselined, worker gets paid $10/hr. On the status date, the worker says "I
am 25% complete, but it has taken me 30 hours to get this far." The problem
is that if I enter 25% complete into project, the Actual Work column changes
to 20 hours. This is incorrect ... his actual work is 30 hours. If I change
Actual work to 30 hours, the %Work Complete changes. Wrong. If I enter an
Actual Cost of $300, the CPI calculates correctly. However, I am being
mislead in that I am inferring that 20 hours of "real work" cost me $300. In
reality, I may have underbid the task and assumed the worker was more
efficeint than actual performance.
It is my opinion that I should be able to take "time card data" or "actuals"
from a separate accounting system and send these to Actual Work/Actual Cost
and have things calculate correctly. Otherwise, I am leaving it up to my
worker to say... "Well, I am 25% complete but I have only been working x% as
effectively as my bid so my ACWP is $300 or 30 hours"
I feel I need a better match between Actual Work and Actual Cost. Actual
Work (to me, time card values) has very little to do with the Work
Completed... work completed is BCWP and it has nothing to do with cost or a
time card entry.
So, please agree or educate me. Thanks
jim
I feel we need to be able to take "time card data" and enter it in to actual
work.
----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.
http://www.microsoft.com/office/com...afa9-2dea60746828&dg=microsoft.public.project