Do not migrate Global Data to project server 2007

B

barbara.korte

Hi,

I have a Project Server 2007 already installed on one server, and I
want to migrate only the projects of Project Server 2003, without the
enterprise global template.
Is there any way to migrate the projects and not the global data of
Project Server 2003?
I have read that if I don't especify the MigrateAll parameter, it will
migrate only the global data, but if I configure it to save or
publish, it also migrate the enterprise global template.
Can anyone help me?

Thanks
 
B

Ben Howard

The P12migrationtool.exe will migrate the EGT as you have stated. So, your
only option is to save the 2003 project to an MPP file, and then import it
into 2007 (Tools | Enterprise Options | Import). You'll need to map
resources and other such items, but crucially, you won't need to import the
EGT.

HTH,
 