C
Carl Morley
Hi,
I've got some particular tasks that take about 6hrs. But they must be
completed within 1 day. If there is not enough time to complete that 6hr
task on any given day, then MS Project should bump the task to the start
of the next day.
eg. on a day when there is 4hrs of another task at the start of the day,
there is not time within that same day to complete the 6hr task. However
the way I've got Project set up, it simply schedules 4 hrs of the 6 on
that same day, and then the remaining 2 hrs the following day.
Any idea how I can prevent this behaviour and tell Project that certain
tasks _must_ be completed within the one day?
Regards,
Carl.
I've got some particular tasks that take about 6hrs. But they must be
completed within 1 day. If there is not enough time to complete that 6hr
task on any given day, then MS Project should bump the task to the start
of the next day.
eg. on a day when there is 4hrs of another task at the start of the day,
there is not time within that same day to complete the 6hr task. However
the way I've got Project set up, it simply schedules 4 hrs of the 6 on
that same day, and then the remaining 2 hrs the following day.
Any idea how I can prevent this behaviour and tell Project that certain
tasks _must_ be completed within the one day?
Regards,
Carl.