M
Matt Kennedy
We have an ongoing problem of Project Pro crashing requiring that any oepn
projects be "checked in". This happens almost daily to some and on some
regular basis to all. Do others have this same problem and just live with it?
I've not seen much in here written about this.
I am the PS administrator and have to use PWA to force a check-in of peoples
projects in regularly that is why I am so aware of this. The problem is (it
happens to me as well) that project crashes without warning and not always
when you are doing the same thing. You get the old dialog asking if you want
to send an error report to microsoft or not and then it restarts project.
This obviosuly requires then doing a forced checkin of any plans that were
open when this happened. This happens at least once a day to me personally
and sometimes more. We've all learned to save frequently so there is not a
lot of lossed productivity but I am concerned that it is giving project
server a bad rap (this wasn't happening prior to our transition to project
server a few months ago). I have had the system manager run the various tools
in the resource kit to determine if any project server tuning is required and
have also had the networks team verify that there was no network "hiccup" at
that particular time. We really feel like we have no where else to go with
this at this point.
Do others experience this same behavior in your installations? Is this
somthing we'll just have to live with? Any ideas on things we can do to
proactively track this down?
Thanks!
-Matt
projects be "checked in". This happens almost daily to some and on some
regular basis to all. Do others have this same problem and just live with it?
I've not seen much in here written about this.
I am the PS administrator and have to use PWA to force a check-in of peoples
projects in regularly that is why I am so aware of this. The problem is (it
happens to me as well) that project crashes without warning and not always
when you are doing the same thing. You get the old dialog asking if you want
to send an error report to microsoft or not and then it restarts project.
This obviosuly requires then doing a forced checkin of any plans that were
open when this happened. This happens at least once a day to me personally
and sometimes more. We've all learned to save frequently so there is not a
lot of lossed productivity but I am concerned that it is giving project
server a bad rap (this wasn't happening prior to our transition to project
server a few months ago). I have had the system manager run the various tools
in the resource kit to determine if any project server tuning is required and
have also had the networks team verify that there was no network "hiccup" at
that particular time. We really feel like we have no where else to go with
this at this point.
Do others experience this same behavior in your installations? Is this
somthing we'll just have to live with? Any ideas on things we can do to
proactively track this down?
Thanks!
-Matt