B
Brian
I am sure it is user error, but I need to find my problem (no smart comments
please).
I am attempting to level multiple (8 files) projects using a common resource
pool.
I use project priorities, task priorities (except 1000), only soft
contraints (no musts), and all my task types are fixed work (majority) or
fixed duration (for meetings).
The total number of tasks is about 5000 with 25 resources. Each task is
assigned multiple resources.
Leveling many times leaves
1) resources overallocated within a week (using day to day)
2) large gaps where resources aren't utilized at all.
It appears that 2) is caused by MSP requiring that all the resources start a
task on the same data.
-----that is not necessary for these software development tasks.
-----Can I change this behavior with some setting I can't find?
I also need help with 1).
Thanks for any and all help.
I hate manually leveling this many tasks. :-O
please).
I am attempting to level multiple (8 files) projects using a common resource
pool.
I use project priorities, task priorities (except 1000), only soft
contraints (no musts), and all my task types are fixed work (majority) or
fixed duration (for meetings).
The total number of tasks is about 5000 with 25 resources. Each task is
assigned multiple resources.
Leveling many times leaves
1) resources overallocated within a week (using day to day)
2) large gaps where resources aren't utilized at all.
It appears that 2) is caused by MSP requiring that all the resources start a
task on the same data.
-----that is not necessary for these software development tasks.
-----Can I change this behavior with some setting I can't find?
I also need help with 1).
Thanks for any and all help.
I hate manually leveling this many tasks. :-O