R
Robin Roe
Hi
On almost all of our Programmes we include admin tasks such as Project
Management. These tasks need to last the entire duration of the programme
even though actual time may be put against it only once a week. Unfortunately
Project for obvious reasons calculates this to the critical path, which in
real life it isn't. I have tried using a recurring task but it isn't suitable
for our needs. Is there a way that project can ignore certain tasks when
calculating the critical path?
Thanks
On almost all of our Programmes we include admin tasks such as Project
Management. These tasks need to last the entire duration of the programme
even though actual time may be put against it only once a week. Unfortunately
Project for obvious reasons calculates this to the critical path, which in
real life it isn't. I have tried using a recurring task but it isn't suitable
for our needs. Is there a way that project can ignore certain tasks when
calculating the critical path?
Thanks