F
Faisal Masood
In PWA My Tasks 'Show Only Current Tasks' check box works as per Current
Tasks Displayed Setting under Server Settings (default to 10 days).
Is there a way to automatically hide successor task in PWA > My Tasks as
long as the predecessor task has not yet completed for a Finish to Start
relationship?
TaskA
|
|-> TaskB
If the successor task falls within the Current Task Displayed range of 10
days, then both tasks show up for the resource in My Tasks page even with the
'Show only Current Tasks' option checked.
Need some ideas!
Tasks Displayed Setting under Server Settings (default to 10 days).
Is there a way to automatically hide successor task in PWA > My Tasks as
long as the predecessor task has not yet completed for a Finish to Start
relationship?
TaskA
|
|-> TaskB
If the successor task falls within the Current Task Displayed range of 10
days, then both tasks show up for the resource in My Tasks page even with the
'Show only Current Tasks' option checked.
Need some ideas!