M
Michael Hsing
Hello,
It seems by default the longest task (by the same resource) will start first.
For example,
1. Create task1 with duration of 2 days.
2. Create task2 with duration of 4 days.
3. Assign r1 to task1. It shows task1 starts on 10/27.
4. Assign r1 again to task2. Now task2 will start on 10/27, and task1 will
start on 11/2.
Is there an option I can specify that the task I add first ( like task1)
will start first, if I don't specify any dependency/predecessors between the
tasks?
Thanks for the help.
Regards,
Mike
It seems by default the longest task (by the same resource) will start first.
For example,
1. Create task1 with duration of 2 days.
2. Create task2 with duration of 4 days.
3. Assign r1 to task1. It shows task1 starts on 10/27.
4. Assign r1 again to task2. Now task2 will start on 10/27, and task1 will
start on 11/2.
Is there an option I can specify that the task I add first ( like task1)
will start first, if I don't specify any dependency/predecessors between the
tasks?
Thanks for the help.
Regards,
Mike