R
Rob List
Hi,
I want to use project as a cross-company management tool, but this is rather
hard as you can't double book people.
For example, i know that Bill is scheduled for 2 days a month of meetings,
which is 24 days during the period of 01/01/2005 and 31/12/2005 - problem is,
if i set that kind of timescale, Project thinks the task is 260 days long -
which it isn't.
The other problem I have is double booking people. Obviously if Bill is
doing 24 days between now and the end of the year in meetings, I hope he's
going to be doing something else for the remaining 236 days (even if he is a
lazy bugger), but when I try and do this it tells me Bill is double booked.
Any ideas? I'd love you forever if you could sort this for me - if you were
in London, I'd buy you a pint!
I want to use project as a cross-company management tool, but this is rather
hard as you can't double book people.
For example, i know that Bill is scheduled for 2 days a month of meetings,
which is 24 days during the period of 01/01/2005 and 31/12/2005 - problem is,
if i set that kind of timescale, Project thinks the task is 260 days long -
which it isn't.
The other problem I have is double booking people. Obviously if Bill is
doing 24 days between now and the end of the year in meetings, I hope he's
going to be doing something else for the remaining 236 days (even if he is a
lazy bugger), but when I try and do this it tells me Bill is double booked.
Any ideas? I'd love you forever if you could sort this for me - if you were
in London, I'd buy you a pint!