Downloading standard holidays into Project

E

Erik

Is there a way to download standard US holidays into Project 2003 such that
they show up as non-working days in the project calendar?
 
D

Dale Howard [MVP]

Erik --

There is no automated way to do this in Microsoft Project. You must
manually add the holidays to the appropriate calendar. Sorry.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 
R

Rod Gill

Easiest way is to edit the Standard calendar on one PC, then use the
Organizer to over write the standard calendar in your Global.Mpt file. Copy
the project with modified Standard to other PCs so they too can use
Organizer to update their Global.Mpt files. Help has more info on this.
 