K
kgrigio
I have a task that needs to finish on a certain date and I have a bunch of
predecessors that must happen prior to the final task finishing. How can I
drive all the precedessors start dates based off the final task? This is
kind of the opposite of how project works, I know, but basically I want to
know when all of the work has to start based off the final end date.
Here is an example of what I am asking, just in case I am not clear.
Task 1 (5 days)
Task 2 (10 days)
Final task must finish on specific day
I want project to move task 2 automatically to start 10 days prior to the
specific final task being completed and task 1 to start 5 days prior to this.
Any way to do this wth project?
predecessors that must happen prior to the final task finishing. How can I
drive all the precedessors start dates based off the final task? This is
kind of the opposite of how project works, I know, but basically I want to
know when all of the work has to start based off the final end date.
Here is an example of what I am asking, just in case I am not clear.
Task 1 (5 days)
Task 2 (10 days)
Final task must finish on specific day
I want project to move task 2 automatically to start 10 days prior to the
specific final task being completed and task 1 to start 5 days prior to this.
Any way to do this wth project?