Driving Links

L

LS123

Hi,

Is there a way in MSP project to show "only" the driving links between
predecessors & Successors.

OR

Can we put some kind of formulae in any of the text or number fields to get
the IDs of driving activities? We can show these along the gantt bars to
reflect which activities are driving a particular activity.

Thanks in Advance.
 
P

Projectability

If you are using Project 2007 the "Task Drivers" feature available from the
Project Menu and the Standard Toolbar will illustrate which predecessor task
influences the currently selected task.

--
Dominic Moss

Projectability - Helping People achieve more with Microsoft Project

Check the Downloads section on our Website for useful documents on both
Project Management and Microsoft Project

www.projectability.co.uk

Why not subscribe to our monthly newsletter for hints tips and views

http://visitor.constantcontact.com/manage/optin/ea?v=001WVdpo956d6lHqIISFtfgVw==
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top