F
farzim
Hi,
I would like to have the driving predecessor highlighted for tasks with
multiple predecessors as in P3 where the driving predecessor is
highlighted with *. Is it possible in msp2003 or are there any macros to
enable this.
Thanking you in advance.
I would like to have the driving predecessor highlighted for tasks with
multiple predecessors as in P3 where the driving predecessor is
highlighted with *. Is it possible in msp2003 or are there any macros to
enable this.
Thanking you in advance.