J
JimEvens
Hello. I am trying to add multiple task bars to one task. IE I have a
Design Time and a Install time. Originally I did Design time + install
time = during (days) and got the bar that came up. However. I would like
to seperate these two so you can see maybe design time in blue and
install time in red. I did use the split function but any other features
that would make this more or so to scale say if design time is only 1
day and install time is 35. Okay Thank you very much.
Design Time and a Install time. Originally I did Design time + install
time = during (days) and got the bar that came up. However. I would like
to seperate these two so you can see maybe design time in blue and
install time in red. I did use the split function but any other features
that would make this more or so to scale say if design time is only 1
day and install time is 35. Okay Thank you very much.