I'm getting tasks in the employee's My Tasks view that have been reassigned
to someone else. It shows up correctly in the Project view. The only way I
have found to correct it is to SaveAs Project1 to Project2, delete Project1,
SaveAs Project2 to Project1, delete Project2.

1. I Publish New and Changed Assignments nightly. What am I doing wrong?

2. Is there a way to find the duplicate assignments easily? On over a
hundred active projects, there is no way for me to know.

3. Is there an easier way to delete them other than the process I described
above?

The project manager uses the project data while the employee uses the
assignment view. This problem can cause confusion and inefficiency. Please
help!

Thanks in advance for any response.

--Conrad Santiago
 