C
Connie
I am working to integrate 3 schedules and create a Master Project Schedule.
My problem is that 1 schedule will be working 8 hour days. The 2nd is
working 14 hr days and the 3rd goes from a 24 hour scheduled workday.
Does anyone have any suggestions of what I can do? The Master converts
everything to the original 8 hour workday because that is what the 1st
schedule is using.
I can't rely on the info being imported.
I need help. Any ideas??
My problem is that 1 schedule will be working 8 hour days. The 2nd is
working 14 hr days and the 3rd goes from a 24 hour scheduled workday.
Does anyone have any suggestions of what I can do? The Master converts
everything to the original 8 hour workday because that is what the 1st
schedule is using.
I can't rely on the info being imported.
I need help. Any ideas??