S
Shawn
I have two projects (ProjA and ProjB) that each have tasks
that are linked to tasks in the other project. Both MPP
files are in the same folder on a network share.
Consider this scenario (6 bullets):
(1) Task 3 is ProjA has a predecessor of Task 7 in ProjB.
(2) I copy ProjB to my local drive to edit it.
(3) Task 7 becomes Task 14 because I added new tasks.
(4) I paste the updated ProjB back to the share (replacing
the original, older version).
(5) Task 3 in ProjA seems to have automatically updated to
reflect the fact that Task 7 in now Task 14 in Task B.
That's good.
(6) However, ProjA seems to now have a second predecessor
for task3, which is the copy of the Plan B that is still
on my C:\ drive. In other words, when I copied Plan B to
my C:\ drive and then pasted it back, MS Project gave Proj
A an extra predecessor.
So, my question is how can I copy linked projects to my
local drive for modification and then stick them back on
the share without losing links or creating duplicate links?
Thanks
- S
that are linked to tasks in the other project. Both MPP
files are in the same folder on a network share.
Consider this scenario (6 bullets):
(1) Task 3 is ProjA has a predecessor of Task 7 in ProjB.
(2) I copy ProjB to my local drive to edit it.
(3) Task 7 becomes Task 14 because I added new tasks.
(4) I paste the updated ProjB back to the share (replacing
the original, older version).
(5) Task 3 in ProjA seems to have automatically updated to
reflect the fact that Task 7 in now Task 14 in Task B.
That's good.
(6) However, ProjA seems to now have a second predecessor
for task3, which is the copy of the Plan B that is still
on my C:\ drive. In other words, when I copied Plan B to
my C:\ drive and then pasted it back, MS Project gave Proj
A an extra predecessor.
So, my question is how can I copy linked projects to my
local drive for modification and then stick them back on
the share without losing links or creating duplicate links?
Thanks
- S