Duplicate Resources on 2007 Project Import from 2003 (with actuals

W

wdritt

I am trying to use the project Import Wizard in migrating Project Server 2003
plans to Project Server 2007 plans.

One big issue I am having, is that some of these plans have actuals and are
in progress, and when I run the import, it is adding both the original
resource 9from 2003 which is spelled first name, last name) as well as the
new resource as it exists in 2007.

I am a bit confused, since I am "mapping" the old resource on the plan to
the 2007 enterprise resource when I go through the wizard.

Migration works much smoother on plans with no actuals entered. Is this a
limitation on a 2007 migration for current projects that originate in 2003 PS?

Has anyone seen this?
 
W

wdritt

One additional note, I do not have the "restrict updates to PWA" option
selected in my 2007 environment
 