Hi All:
Background:
---------------
I am getting an issue in PWA 2007. I am not able to see/add 'Duration' and
'Remaining Duration' fields in 'My Assignment' view under 'My Work' page.
Note: I have 2 instances of PWA 2007. One environment is showing both fields
but other instance NOT.
Questions:
1- Do you know why it is happening and how to solve it? Very annoying...
2- Is it possible in any ways to make remaining Duration Editable field in
Task's detail page under My Work page? My Client wants to enter days in
'Remaining Duration' field when they enter progress against a Task.
I would appreciate for your quick response.
Thank you,
Ijaz Rasheed(EPM Consultant)
Background:
---------------
I am getting an issue in PWA 2007. I am not able to see/add 'Duration' and
'Remaining Duration' fields in 'My Assignment' view under 'My Work' page.
Note: I have 2 instances of PWA 2007. One environment is showing both fields
but other instance NOT.
Questions:
1- Do you know why it is happening and how to solve it? Very annoying...
2- Is it possible in any ways to make remaining Duration Editable field in
Task's detail page under My Work page? My Client wants to enter days in
'Remaining Duration' field when they enter progress against a Task.
I would appreciate for your quick response.
Thank you,
Ijaz Rasheed(EPM Consultant)