K
Kite
I'm running MS Project 2000.
My problem is this. I have a task which will last for the duration of
the (financial) year from 1st Apr to 31st March. So I enter these as
start/end dates, yet Project then defines the duration as being 14.91
months long! Alternatively if I enter a start date and put the
duration as being 12 months the end date is not 12 months away as it
should be.
Any ideas? I can't find any resolution in the date/caldendar options
and I am new to Project though certainly not Office or other MS
products.
Thanks in advance for any help!
K
My problem is this. I have a task which will last for the duration of
the (financial) year from 1st Apr to 31st March. So I enter these as
start/end dates, yet Project then defines the duration as being 14.91
months long! Alternatively if I enter a start date and put the
duration as being 12 months the end date is not 12 months away as it
should be.
Any ideas? I can't find any resolution in the date/caldendar options
and I am new to Project though certainly not Office or other MS
products.
Thanks in advance for any help!
K